The walls are finished, well, kind of. The exception is the large hole in the back wall which remains open for equipment access.

  The guys finishing the last bit of block for the east wall.

The guys finishing the last bit of block for the east wall.

  Looking down the west side of the house, the driveway and pathways are nearly set for concrete. Looking forward to having something other than dirt for clients to walk in on!

Looking down the west side of the house, the driveway and pathways are nearly set for concrete. Looking forward to having something other than dirt for clients to walk in on!

  The cable coming out of the ground will feed the large transformer that the city requires. Behind you can see the beginnings of a fire pit / seating area we will be putting in the front yard.

The cable coming out of the ground will feed the large transformer that the city requires. Behind you can see the beginnings of a fire pit / seating area we will be putting in the front yard.

  This will be the new main entrance to the studios. I was really impressed with how the masons worked around the old eaves with the block.

This will be the new main entrance to the studios. I was really impressed with how the masons worked around the old eaves with the block.

IMG_0357.jpg
  Today the underground work started. This photo shows the plumbers tying into the new sewer line from the new janitor closet and bathroom. They finished most of their work today so the rest of the week should be the electricians who have a lot to do. We will also be running conduit to carry lines from the house into the studios and between the studios, as well as the lines that go from the racks to the consoles and the machine rooms.

Today the underground work started. This photo shows the plumbers tying into the new sewer line from the new janitor closet and bathroom. They finished most of their work today so the rest of the week should be the electricians who have a lot to do. We will also be running conduit to carry lines from the house into the studios and between the studios, as well as the lines that go from the racks to the consoles and the machine rooms.

  The new lobby on the right and the studios spaces / bathroom / janitor closet on the left.

The new lobby on the right and the studios spaces / bathroom / janitor closet on the left.

  Plumbers getting the drain lines installed, door on the right is lobby into the janitor closet, door on the left is lobby into the bathroom. the large opening is lobby into the hallway which will run between studios.

Plumbers getting the drain lines installed, door on the right is lobby into the janitor closet, door on the left is lobby into the bathroom. the large opening is lobby into the hallway which will run between studios.