#29

I’m really getting sick of drywall dust. We did our best to put up plastic and keep the house safe from dust, but there is no escaping it, it is everywhere. Luckily we are getting really close to the end of this stage.

We are about a week from having most of the drywall done, with the exception of the soffits that will need to be built around the HVAC duct.

Getting the new HVAC run into the house, upstairs and down.

Getting the new HVAC run into the house, upstairs and down.

Our metal railing for the instrument storage room arrived and was installed this week.

Our metal railing for the instrument storage room arrived and was installed this week.

We also got the railing for the stairs into the lobby from the house but they have to re-do something about it due to it not meeting ADA requirements.

We also got the railing for the stairs into the lobby from the house but they have to re-do something about it due to it not meeting ADA requirements.

The instrument room with the railing installed.

The instrument room with the railing installed.

We removed the metal grid that fills this opening between the house and the new space in order to have some metal trim installed, expecting that to return tonight.

We removed the metal grid that fills this opening between the house and the new space in order to have some metal trim installed, expecting that to return tonight.

Tracking room 2 with the ceiling grid hung and ready for sheetrock.

Tracking room 2 with the ceiling grid hung and ready for sheetrock.

First of three layers of sheetrock going up in tracking room 1.

First of three layers of sheetrock going up in tracking room 1.

f39ccd26-9c73-4230-b212-72462b9346a9.jpg
First layer going up in control room 2.

First layer going up in control room 2.

Tracking room 1 layer #1 finished and starting layer #2.

Tracking room 1 layer #1 finished and starting layer #2.

Tracking room 2 ceiling complete minus final taping/mudding.

Tracking room 2 ceiling complete minus final taping/mudding.

Power for lighting in the tracking room 2 soffits above the door into the sound lock.

Power for lighting in the tracking room 2 soffits above the door into the sound lock.

Control room 1 sheetrock complete minus taping and mudding, and my son Truman.

Control room 1 sheetrock complete minus taping and mudding, and my son Truman.