Sheet rock and landscaping this week. They are nearly done with the third layer of sheetrock everywhere now so I suspect they will start working on the ceilings soon.
#25
Spring is approaching and we have more rain and less snow around here. We are starting to get studio bookings that could be after the new spaces are open, but it’s still pretty hard to know exactly when that will be.
#24
Preliminary wiring (electrical, audio, network/security) is finished and we are now heading into weeks (months?) of sheetrock work. In most cases walls have 3 layers of taped and mudded 5/8” sheetrock per side, although some walls only get two layers. Regardless it will take a while to complete.
We remain busy in the “house” studio although with the temporary wall out back removed the construction noise is encroaching.
I’ve begun to lose sleep due to worry about how we are going to afford to keep the doors open, but at this point, what can you do but move forward?
#23
Things are creeping along, there is still so much to do, and so much that can be done but we still have days where only one sub or even none show up. Our contractor is frustrated and working hard to get them out but there is so much building going on that it makes it hard to keep subs on site.
#22
Last week was filled with more rough electrical, hvac, insulation and network/security wiring. We passed our ‘power to panel’ inspection so we are just a few days away from having power out in the new space and being able to swap the house power over to the new distribution panel.
I spent a fair amount of time this week thinking about and discussing colors and finishes with Wes. I tend to be pretty particular with color and I’m really worried about getting it wrong, especially considering that what you see in the control rooms will be almost entirely wood or fabric, and fabric panels are a lot harder to change than paint. Wes has so much experience designing studios and refining things to make these very odd shaped spaces feel natural and normal and it’s easy to just want to throw colors all over without thinking through just how that will feel when you are in the studio day after day. I think at this point we are pretty close to having things pinned down and with no time to spare, Tony Brett is diving into building our acoustic panels.
Tomorrow Thom Canova will arrive to spend a week doing the rough/pre-wiring for the lines that go in the walls. After that insulation in the walls can begin and then straight into sheetrock.
#21
Two highlights from this last week -
1) while showing a good friend, composer & longtime collaborator the studio build, he said “scott, you’re the only person i know who is bullish on the music industry.”
2) mid-mixing session for a great artist we took a quick tour of the space and she said something to the effect of “i’m excited that we will get to have something like this in Provo, Utah”
Honestly, i don’t know how I feel about the music industry as a whole, but I know that there is a lot of great music being made here in Utah and we are lucky to get to be a part of it. We have remained busy for a long time now and while this really is a crazy business move, I’m really happy to be able to do what I can to provide this great music scene with such a place. We are lucky to have Wes Lachot, Tony Brett and Thom Canova on board and frankly doing us such a favor by working long and hard on a project with some pretty big budget/time constraints. They are working closely with our great contractors at Zadok Construction (Nick and Jared) to build a pretty amazing studio space.
…and you should really check out some of the great music coming out of Utah:
https://www.thenationalparksmusic.com/
http://www.theholleringpines.com
https://nymph-music.bandcamp.com/releases
These are just the artists we’ve worked with in the past month.
#20
There has been a lot going on over the past couple weeks, but most of it doesn’t make for great photos so Ive been a bit quiet. Problem is, if I don’t keep updating this Ill get too lazy and drop it forever (plus my dad keeps asking me for an update), so here is some of what has been going on:
#19
I’ve been giving a lot of tours of the construction site lately. Without fail everyone asks when we expect to be finished and ready to move in. The truth is I have no idea. At one point I was hoping it would be March, now I’m hoping it’s May, but really, no idea. Honestly, for now as long as people continue to show up and work every day I’m happy.
#18
Busy week and weekend in the studio, but things continued out back in the new space. Most of the progression this week was in electrical, but there was a lot of leftover framing done, as well as many meetings regarding hvac and sheetrock.
#17
Happy 2019! It has been a while since my last update, but given the holidays things slowed down considerably. Last week however that really changed. We were lucky to have Tony Brett from Brett Acoustics in from North Carolina to train the framing crew in the complex art of control room construction.
At this point most of the major framing is done so electrical / hvac and even the audio wiring should really get under way soon.
#16
Some new walls this week have started to reveal the studio spaces, it has also revealed some pretty massive areas that are unused, namely above the booths in studio 1 and above the booth of studio 2, the bathroom and the janitor closet. The space above the booths in studio 1 has close to 10’ ceilings and is roughly 25’ x 10’!
Anyway, just trying to figure out if there is something useful that can be done with that space. Some ideas we have come up with; storage for the emt plates, general storage for random stuff, echo chamber(s).
I’d love to do some echo chambers but it means more framing, more sheetrock or plaster, more money. Anyone else have any ideas?
#15
More snow here in Utah, and definitely cold, most days hover in the low 30’s. Everyone keeps working hard and we are looking forward to our first visit from Tony Brett and Brett Acoustics in early January. Here’s what has happened since the last update:
Finally moved the time-lapse cameras so we could keep capturing the work going on within the walls. The video below is updated to show the work through November 30. I was really hoping to capture the trusses being set but due to the cold weather the batteries died quickly and the cameras were out the day before the trusses were delivered! New batteries are in now and the cameras are back on the job, just need to remember to change them more often.
#14
Now that the concrete is ready, framing has begun in earnest. Real snow fell today, so the sooner they get this roof on the better.
More ledger board up as well as bottom plates for the hallway between studios and the wall between the back of control room 2 and the instrument storage room.
#13
Happy Thanksgiving! This was a good week (week and a half) for studio building, it was cold but no rain or snow - next week’s forecast doesn’t look so good.
First of all we have a floor!
#12
Things have been cooling down a lot here in Utah, todays high was 44 and the low was 24. We even had a small amount of snow the other night so we definitely need to get a roof on this place. The underground work finished up with the placement of the pipes that will carry most of the audio lines.
I made another video for you this week, just a basic walk through with the gravel down so it was easy to see where the rooms laid out. I have absolutely no business using these video editing programs (premier pro, after effects) but it’s fun to mess around with, even though what should have taken someone 30 minutes took me 5 hours. Nonetheless, enjoy…
#11
The walls finally are tall enough to block the time-lapse cameras so it’s time to move those to a new location. Here is a time-lapse of our build thus far:
#10
The walls are finished, well, kind of. The exception is the large hole in the back wall which remains open for equipment access.
#9
We are just 3 courses of block from of the walls. There is still a large opening in the back of the building - kept there for access to the inside. That hole will be filled once the underground work starts next week.
Today the structural steel showed up. These beams will support the weight of the roof surrounding the house - nothing will bear on the old walls, the roofs will just be tied together.
Looking forward to reaching the final height on the walls tomorrow and also to beginning work on the front landscaping. Still managing to keep working in the house, mixing and recording.
#8
The walls are nearly there, the lobby area has reached the top and the studio section has 8 feet left to go. We expect the block to be finished this week, with the underground work (plumbing, electrical, audio) to follow right after.
#7
One week later and things are beginning to change - it finally looks like something is being built!
Before I get into that, one thing I forgot last week...before the footings were backfilled, Dave, one of the superintendents, remembered that I was hoping to have the ability to run a digital snake out of the building. The studio shares a block with Velour Live Music Gallery, which is the premier local music club and with a cat 5 cable as a digital snake we will be able to split the stage feed and multitrack local shows. Dave grabbed a drill and got some conduit through the stem wall so we can have a cable buried and get into the building without having to go through a door.
Monday - rough grading and compacting was completed, concrete block arrived and was laid out.
Tuesday - the walls started going up
Wednesday - more block went up until the walls reached the height of the first “lift” (four feet).
Thursday - scaffolding began to be set up and the concrete truck showed up to grout the first lift. The walls will be completely filled with concrete which is good for sound but bad for the guy who someday wants to knock the place down.
Friday - more block, got close to the second lift, including the stripes of charcoal colored block which, although likely futile, are an effort to draw attention away from just how enormous and prison-like the outside of this building is going to be.
We went through a number of different options for the stripes on the building.
This week we also spent time planning for landscaping, scheduling with Brett Acoustics and Canova Audio, and laying out the security and access systems.
Will we get to the top of the wall this coming week? Stay tuned to find out.